HOME IS WHERE
LIFE HAPPENS

Seiken Victoria

SEIKEN VICTORIA

ASHOKAPURAM, CALICUT (Near Christian College)

  • Residential Apartments
  • 2&3 Bedroom Apts
  • Ashokapuram, Calicut (Near Christian College)
  • Ongoing Project

Permit No: TP11/111075/14

  • SPECIFICATIONS
  • AMENITIES
  • FLOOR TYPES
  • GOOGLE MAP
  • LOCATION DETAILS
  • PROGRESS

Flooring

  • Flooring
  • Vitrified tile flooring for entire apartment
  • Balcony Area: Ceramic tile flooring

Kitchen

  • Kitchen
  • Kitchen counter with granite top and single bowl sink with single drain board.
  • Ceramic tile above counter to a height of 60cms.

Toilet

  • Toilet
  • Ceramic tile flooring
  • Toilet wall with ceramic tile up to false ceiling.
  • Premium quality CP fittings.
  • Wall hung sanitary fixtures with concealed cistern in all toilets.

Doors/Windows

  • Doors/Windows
  • Solid timber entrance door.
  • Flush door for bedrooms.
  • Powder coated aluminum windows.

Painting

  • Painting
  • Putty and plastic emulsion for internal walls.

Electrical

  • Electrical
  • Concealed conduit wiring, adequate light and fan points, 6/16amps socket points etc controlled by ELCB and MCBs

Lift

  • Lift
  • Two fully automatic lifts.

Generator

  • Generator
  • Generator back up for common facilities such as lifts common lighting, pumps etc. Generator back up for designated points in the apartment.

Elegant and Spacious Lobby

Swimming pool

Intercom facility

Fitness Center

Round the clock security

Type A

3 Bedroom(s)

1742 Sqft

Type B

2 Bedroom(s)

1142 Sqft

Type C

3 Bedroom(s)

1591 Sqft

  • Mini Bypass: 600 mtrs
  • Baby Memorial Hospital: 1.5 km
  • Providence School: 1.5 kms
  • Malabar Christian College: 1 km
  • Railway Station: 2 kms
  • Bus Stand: 2 kms
  • Super Markets: 500 mtrs
  • Sarovaram Bio Park: 2 kms
  • Calicut Beach: 3 kms
  • Mosque: 500 mtrs
  • Church: 500 mtrs
  • Temple: 500 mtrs
Elevation Completed.
Flooring layout in progress.
Interior painting work in progress.
Bath tile works almost complete.
A. Masonry works completed up to 13th Floor
B. Internal Plastering completed up to 5th Floor
C. Electrical work completed up to 9th Floor
Laterite masonry work is in progress – 12th floor
Laterite masonry work is in progress – 12th floor
Sunshade concrete work progressing – 13th floor
Sunshade concrete work progressing – 13th floor
Electrical work progressing – 2nd floor
View From Eleventh Floor